Editor’s note: This story was updated on March 9 with legislation introduced in three states, Michigan, Minnesota, and Pennsylvania, and information about a proposal in Denver, Colorado.
For years, state policymakers mostly treated hyperscale data centers as a race: bigger tax breaks, faster approvals, and fewer questions.
In 2026, a different pattern is emerging. From Illinois, as Gov. JB Pritzker proposes suspending tax incentives for data centers, to Texas, where counties debate data center moratoriums with the state government, more legislatures and policymakers are reaching for a tool usually reserved for crisis moments: a moratorium–a formal pause on new data center projects–while states sort out what this industry is doing to electric grids, water supplies, land use, and public budgets.
We are now tracking at least 12 in-session states with filed data center moratorium bills this cycle (in addition to other states considering executive action and many cities and counties considering local measures). It’s a signal that the political system is starting to acknowledge the obvious: hyperscale data centers are huge, fast-moving, and highly subsidized, and states often lack basic economic and environmental guardrails to protect residents and ratepayers.
Where moratorium bills are filed (as of March 9, 2026):
Georgia
HB 1012, would bar counties and cities from issuing any permit, license, or certificate that would authorize the construction or development of a new data center until March 1, 2027, with an exception for approvals issued before July 1, 2026.
Maryland
HB 120 would prohibit construction of new data centers (and prohibit state or local approvals for construction) unless/until the General Assembly enacts specified legislation related to co-location with new or existing power generation (including natural gas, nuclear, or small modular reactors, or SMRs).
The Wolverine State has introduced a statewide data center moratorium proposal in the Legislature and House Resolution 240 urges a temporary pause on discretionary state incentives for data centers.
Minnesota SF 4298 would bar state and local governments from issuing permits for data centers until one year after the Public Utility Commission submits a comprehensive report on possible data-center development scenarios in the state.
New Hampshire
HB 1265 would prohibit anyone from beginning construction of a new data center anywhere in the state for one year from the act’s effective date. The bill also creates a legislative committee to study the environmental impacts of data centers.
New York
S9144 would impose a statewide moratorium on permits for new data centers and direct the Public Service Commission to minimize impacts on electricity and gas rates.
Oklahoma
SB 1488 would establish a moratorium on building new data centers until November 1, 2029, while directing the Oklahoma Corporation Commission to study impacts on water supply, utility rates, property values, and siting.
H. 5286 (Session 2025—2026) is a joint resolution that would bar state and local governments from granting permits, approvals, or incentives for new data centers until January 1, 2028.
South Dakota
SB 232 would impose a one-year moratorium on the construction or expansion of hyperscale data centers. HB 1301 would impose a moratorium while also addressing cost/risk allocation tied to electricity use by data centers.
Vermont
S.205 proposes a temporary moratorium on “AI data centers” while regulators study impacts and recommend a regulatory framework (the introduced bill text sets the moratorium through July 1, 2030).
Virginia
HB 1515 would prohibit localities from granting final approvals for rezonings/special permits/site plans for new data centers until specified grid-interconnection conditions are met or a date certain.
Wisconsin
Wisconsin lawmakers have circulated draft legislation (LRB-6377/1; also referenced with LRB-6391) that would create a statewide moratorium on data centers by prohibiting operation of a data center unless the legislature first enacts a package of protections—such as a statewide planning authority and explicit bans on shifting data center energy and water costs onto residential customers.
*Additional moratorium bills are being discussed in Minnesota, Pennsylvania, and other states and we will update this post as those bills are filed.

Why moratoriums are suddenly “on the table”
- Grid shock and cost shifting: massive new “large load” demand colliding with transmission constraints and interconnection backlogs—raising the question of who pays for upgrades and reliability. In the PJM region, UCS found that ratepayers in seven PJM states were on the hook for $4.3 billion in electricity infrastructure projects approved in 2024 solely to connect data centers—a concrete example of how connection costs can be socialized.
- Local backlash: land conversion, noise, diesel backup generation, water use, and a sense that communities are being told “you don’t get a say.”
- Budget alarm bells: from Georgia estimating $2.5 billion in losses to data center tax breaks in a single year to Virginia ($1.6 billion) to Texas ($1 billion), many states are discovering that open-ended sales tax exemptions for servers and equipment can become a fiscal escalator—especially as AI drives bigger builds and more expensive equipment purchases.
- Read more: “Cloudy with a Loss of Spending Control: How Data Centers Are Endangering State Budgets.”
A pause is not a plan, but it’s a wake-up call
A moratorium doesn’t solve the underlying policy failures. But it does tell you something important: lawmakers are realizing they’ve been asked to sign off on a growth model that can impose long-term public costs (grid upgrades, rate impacts, water and land pressures) while delivering thin job creation and huge tax losses.
Local governments are not waiting for state capitols: at least 63 local data-center moratorium actions have been introduced, considered, or adopted across dozens of towns and counties. Some 54 have already passed (often as short “time-out” freezes while zoning and utility-impact rules are rewritten), while nine more are introduced/proposed or under active consideration.
Recently, the the city of Denver, Colo. announced a moratorium on new data centers to reassess regulations, aiming to balance tech growth with environmental and community impact and the city of Ypsilanti, Mich., passed a data center moratorium, using emergency action to pause approvals while the city evaluates zoning and infrastructure impacts. Taken together, the local wave is a warning flare to state lawmakers: if states won’t set guardrails, communities will keep hitting the pause button themselves, one data center project at a time.